Notice of Construction - Chemong Bridge Shoreline Restoration - James A. Gifford Causeway

Posted on Wednesday December 15, 2021

Please be advised that the County of Peterborough is proceeding with repairs to the shoreline of Chemong Lake under the Chemong Bridge on the James A. Gifford Causeway.

Work will commence the week of December 13, 2021, and is expected to be completed by the end of January 2022. Please note that unfavourable weather conditions may influence the work schedule.

The County’s contractor, Drain Bros Excavating Ltd., will be repairing scour damage that has occurred to the shoreline and embankments of Chemong Lake

Two lanes of traffic will remain in service during this period. Motorists should exercise additional caution for pedestrian, cyclist, and construction worker safety with construction vehicles taking access from the Causeway on the north side of the bridge.

If you have any questions, please contact the following individuals:

Steve Taylor, P.Eng.
Consultant Project Manager BT Engineering Inc.
100 Craig Henry Drive, Suite 201
Ottawa, Ontario K2G 5W3
Phone: 613-228-4813
Email: steven.taylor@bteng.ca

Peter Nielsen, CET
Manager, Capital Projects
County of Peterborough
470 Water Street
Peterborough, Ontario K9H 3M3
Phone: 705-775-2737 ext. 3200